Tuesday, March 25, 2014

Basement Stairs, Plumbing, Electrical


Inside the kitchen.  More blue electrical boxes going in, and some roughed-in plumbing for the kitchen sink.



Electrical wiring.  Already, 1/2 mile of wire has been installed.
 (For real.)
And they're not done yet.
And-- I think the most exciting progress---
Finally, STAIRS to the basement! 

Until now, we've had to trek way around the house, through the snow, or, worse, down an ice-glazed slope to get to the basement.  It is oh-so-much more convenient to have an indoor stairway!  And it's a pretty walk too.


 
From the Stair Landing: The 1st floor and the basement.



View of the 1st floor from the Basement Stairs.
 
Patio door installed in the basement, marking the official end of window and door installation-- they're all in.

Sunny  basement, which we've been enlisted to thoroughly sweep this Saturday. 
The boys spent an evening out here last week, and already have some forts and hide-outs in the works.



Bathtub's been installed.

Laundry room plumbing.

Fast-paced 10 days ahead.  There's a lot of Electrical to be finished to get ready for the scheduled inspection.
Then, after the Inspection, comes Insulation.