Tuesday, October 29, 2013
Breaking Ground
Saturday-- October 26: The Ground-breaking. The excavator worked most of the day to dig the basement, and finished the digging on Monday, the 28th. It looks like a huge footprint...
Gravel
Wednesday October 23, after the driveway passed inspection, the gravel was laid. Driveways done, BRING ON THE EXCAVATOR!!!!!
Thursday, October 24, 2013
A Path in the Woods
Tuesday October 22, we drove up the rough graded driveway for the first time. We saw the clearing in the woods that will hold our new home. The trees and brush are replaced by dirt piles and soft earth that is waiting for the basement to be dug up by the excavator. J. loves the dirt piles and hopes the new house includes them in the package, D. and M. are a tad skeptical that dirt piles will add house value. A. looooves the excavator and bobcat.
The Beginning
Saturday October 12, the house project gets a kick start with the ground breaking of the driveway. Starting from the top the crew will make their way to the road clearing the path as they go.
Subscribe to:
Posts (Atom)