Sunday, July 20, 2014
Siding, Septic, Flooring
| Electrical Panel Complete |
| Well Pump is installed in the Mechanical Room, and powered. We now have water via outdoor hoses (the only faucets that are installed.) |
| Siding continues and continues. Every sunny day. There's just lots of siding. And thank you to all of our invaluable help. |
| Siding "Go-fer." |
| Septic tanks below the house. |
| Septic connection. |
| Septic drain field. |
Sunday, June 29, 2014
Paint, Siding, Well, Electrical
| Cousin Michaela from Alaska came to see the paint colors! (She says it looks like Aunt Lynn's palette... just the look we were going for... : ) This bright yellow is the school room. |
| And a library in deep burgundy. |
| Dining room is sage, which will coordinate with the sage countertops in the kitchen on the left. |
| Master bedroom is two shades of brown. You may believe that I picked the one on the right just because it's chocolate-colored... |
| The laundry room is a beautifully bright blue. Clean and cheery. |
| Stairway to the Loft. (Bet the next time you see it, the stairs will be maple-covered.) |
| Over the Loft stairs. |
| Same deep burgundy in progress over the basement stairs. It took 3 coats to achieve the right deepness. |
| Dining room. |
| We saved this massive Living Room wall for last because we just couldn't settle on the color. Here's a test piece of Copper, which we did eventually choose in the end. The verdict's still out on whether we like it or not! |
| The well driller spent about a week here. Hit water a little sooner than he'd estimated (Yay!) so the well is ~only?~ 390' deep. |
| The bees moved in before we. |
| Well is now finished and the well pump is installed and water line piped to the basement Mechanical Room. |
| Siding is progressing little-by-little. They side any time that it doesn't rain. |
| We procured this flooring, about 1000 s.f. of hard maple, from Craigslist. It is a reclaimed gymnasium floor, and the guys have spent many hours planning and hand-cleaning each piece. It's finally all ready to install. |
| Light fixtures have all been installed. The electrical is moving along. |
| Tile has been purchased and is awaiting installation (and somebody to teach us how to tile floors...) |
| Siding crew. |
| Soffits are going in as they finish siding each side. |
| There-- finished front (except the front door which is going in last.) |
| Siding is this far on the North side. We're looking for volunteers who want to be 5 levels high on the scaffolding to do the tip-top. David's lucky that his brothers-in-law climb like monkeys. |
| The Front Yard is wondering why Landscaping is always last on the agenda. |
| Kitchen. (Note ceiling fans are in.) |
| Copper color in the Living Room. |
| Switches and outlets are popping up everywhere. Electrical is ALMOST done. Few more days. |
| 2 Views from the Front Door. |
Well, you get to see a lot of progress if I only post once-a-month! July should consist of flooring and siding. Stay tuned. |